When it fits
Use this proposal to plan for routine BVLOS. Authorization to fly now comes from the rules in effect today.
What to check by operation
The table shows proposed permit limits. Takeoff weight includes the payload. For the proposed operating certificate pathway, check the comparison below the table.
| Operation | Active aircraft | Maximum weight | Population category |
|---|---|---|---|
| Package delivery | Fewer than 100 | 55 lb | 3 or lower |
| Aerial surveying and inspections | Fewer than 25 | 110 lb | 3 or lower |
| Agriculture | Fewer than 10 | 1,320 lb | 1* |
| Civic interest | Fewer than 25 | 110 lb | 3 or lower* |
| Operations training | Fewer than 10* | 1,320 lb* | 1* |
| Demonstrations | Fewer than 50* | 110 lb* | 2 or lower* |
| Flight testing | No stated cap | 1,320 lb* | 1* |
| Recreation | One | 55 lb* | 3 or lower |
* The FAA could authorize exceptions to the marked limits. The proposal has a separate civic-interest exception for safeguarding lives under imminent threat. Proposed §§ 108.440–108.475
Operating permit or operating certificate?
Operating permit. The FAA proposes a pathway for eight specified uses, each with limits and conditions that reflect its risks. An operator would apply for the type of operation it intends to conduct.
Operating certificate. The proposal expressly lists package delivery, agriculture, aerial surveying, and civic interest. For these uses, greater fleet scale, heavier aircraft, or higher population categories can make a certificate the relevant pathway. The proposal adds requirements such as a training program, validation tests, a communication and ground-risk assessment, and a safety management system.
The FAA says it designed the two pathways to match oversight to risk and scale. See the proposal’s preamble, section VIII, and Subparts D and E.
Walk through a BVLOS surveying program
- Name the operation. A team plans to use drones to inspect a long corridor. Start with the proposed aerial surveying provisions.
- Check the permit limits. Twenty-four active aircraft falls within the proposed fleet limit. The team also has to check loaded aircraft weight and the highest population category along its route.
- Check what changes as you grow. At 25 active aircraft, the team would exceed the proposed permit limit and should review the operating certificate pathway. Compare surveying pathways
People and responsibilities
The proposed operations supervisor would oversee the operator’s compliance and safety. The proposal would exempt recreational permit holders from designating an operations supervisor. The operator would designate a qualified flight coordinator for each flight when the manufacturer’s operating instructions require one. That person would monitor the flight and direct it when needed within the system’s capabilities. Proposed §§ 108.305, 108.310, and 108.475(f)(4)
Ground risk
The FAA proposes using the highest population category that applies along an operation. The categories use estimated people per grid cell and the distance to nearby cells. See the day and night population map and the five categories · Proposed § 108.185
BVLOS under current rules
For an eligible civil operation, see the Part 107 visual line of sight waiver. Paid BVLOS delivery of someone else’s property uses the Part 135 pathway. A qualifying public aircraft flight needs BVLOS terms in its public aircraft authority. FAA UAS airspace guidance
Rulemaking status
The FAA and TSA published the proposal on August 7, 2025. Federal review of the draft final rule was pending as of November 21, 2026. Rulemaking docket · Federal review status
Common questions
What does the 100-aircraft limit apply to? The proposed package delivery permit would allow fewer than 100 active aircraft. Other sectors have their own limits. The preamble describes active aircraft as aircraft used in the operation and listed on the permit application. Proposed § 108.440(f) and preamble § VIII.B.1